Wednesday, April 30, 2025

Update about the road access to Mauna Loa Observatory (GONG/ML site)

Here is the road timeline (as of 28-Mar-2025):
1.  RFP released from DOT to the 2 down-selected and qualified vendors: Mid-April
2.  Bids back from 2 vendors (30-day deadline): Mid-May
3.  DOT proposal review and contract award (6 weeks internal at DOT): July 1st
4.  Period of performance (90 days) for road construction: July 1 to Oct 1 

Camera Deployment

Next EVT camera deployment is planned for 19 May - 2 June 2025. Location - Teide Observatory, Tenerife. So far, camera were deployed at 4 GONG sites: GONG/BB, GONG/LE, GONG/CT, and GONG/UD.

GONG/BB connectivity issues

On 19 July, GONG/Big Bear experienced issues with connecting to the network. Rebooting bbgong workstation did not fix the issue. The team re...