Here is the road timeline (as of 28-Mar-2025):
1. RFP released from DOT to the 2 down-selected and qualified vendors: Mid-April
2. Bids back from 2 vendors (30-day deadline): Mid-May
3. DOT proposal review and contract award (6 weeks internal at DOT): July 1st
4. Period of performance (90 days) for road construction: July 1 to Oct 1
Wednesday, April 30, 2025
Update about the road access to Mauna Loa Observatory (GONG/ML site)
Camera Deployment
Next EVT camera deployment is planned for 19 May - 2 June 2025. Location - Teide Observatory, Tenerife. So far, camera were deployed at 4 GONG sites: GONG/BB, GONG/LE, GONG/CT, and GONG/UD.
Subscribe to:
Posts (Atom)
GONG/BB connectivity issues
On 19 July, GONG/Big Bear experienced issues with connecting to the network. Rebooting bbgong workstation did not fix the issue. The team re...
-
GONG/Learmonth (Australia) took observations of a large two-ribbon flare, which was the source of Earth-directed halo Coronal Mass Ejectio...
-
Here is the road timeline (as of 28-Mar-2025): 1. RFP released from DOT to the 2 down-selected and qualified vendors: Mid-April 2. Bids b...
-
The 246th AAS meeting (joint with the Laboratory Astrophysics and Solar Physics Divisions) took place the of week 8-12 June 2025 in Anchorag...